Câu 71: PMI Risk Management Professional

The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG. What should the project m…

Nội dung câu hỏi

The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG. What should the project manager do first?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Interview the other project manager to learn more details. — đáp án hiện tại
  2. B. Review and update the project schedule.
  3. C. Include the risk in the register and communicate with the stakeholders.
  4. D. Communicate with the client to provide the previous shutdown plan.