Câu 2: PMI Risk Management Professional
A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that there is US$200,000 left in the management reserve. From which of the following sources should the funds be drawn to cover…
Nội dung câu hỏi
A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that there is US$200,000 left in the management reserve. From which of the following sources should the funds be drawn to cover the risk mitigation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Organization management reserve
- B. Unplanned risk reserve
- C. Contingency reserve — đáp án hiện tại
- D. Management reserve