Câu 142: PMI Risk Management Professional

Two companies merge. The executive leadership team for the newly formed company hires a project risk manager to integrate both companies' technology platforms into a single global platform. Since success of this integration project is critical for the new company, the project risk manager determines that risk manageme…

Nội dung câu hỏi

Two companies merge. The executive leadership team for the newly formed company hires a project risk manager to integrate both companies' technology platforms into a single global platform. Since success of this integration project is critical for the new company, the project risk manager determines that risk management is vital. What factors does risk response planning include?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. People, planning, and analysis — đáp án hiện tại
  2. B. People, planning, and avoidance
  3. C. Planning, avoidance, and analysis
  4. D. People, avoidance, and analysis