Câu 146: PMI Risk Management Professional

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project’s risk register and asks the risk manager for an analysis of its effectiveness. What two actions should the risk manager do next? (Choose two.)

Nội dung câu hỏi

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project’s risk register and asks the risk manager for an analysis of its effectiveness. What two actions should the risk manager do next? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Check for risk classification and that probability and impact are identified.
  2. B. Check to ensure that the risk is supported by a Monte Carlo simulation.
  3. C. Check to ensure the risk meeting agenda and supporting documents are distributed. — đáp án hiện tại
  4. D. Check to ensure that risk origin, triggering event, and ownership is identified. — đáp án hiện tại
  5. E. Check to ensure that the risks are gathered using Delphi technique.