Câu 124: PMI Risk Management Professional

In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to the project can…

Nội dung câu hỏi

In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to the project cancellation. How should the probability and impact be characterized for this risk?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Low probability/low impact
  2. B. High probability/low impact
  3. C. Low probability/high impact
  4. D. High probability high impact — đáp án hiện tại