Câu 109: PMI Risk Management Professional
The expected monetary value of a project is above USS1 million. The risk manager is concerned about this situation, and decides to review the related plans and processes to evaluate the degree of variation from the baseline. Next, the risk manager needs to document the results of such an analysis. What is the best doc…
Nội dung câu hỏi
The expected monetary value of a project is above USS1 million. The risk manager is concerned about this situation, and decides to review the related plans and processes to evaluate the degree of variation from the baseline. Next, the risk manager needs to document the results of such an analysis. What is the best document for the project manager to reference to find out where the results of such an analysis should be documented?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Communications management plan — đáp án hiện tại
- B. Issues log
- C. Risk management plan
- D. Lessons learned