A six-month, USS1.2 million project is two months completed. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown risks. Most of the project's reserves have not been spent. The risk manager, who is also the project schedule manager, establishes monthly ris…
Nội dung câu hỏi
A six-month, USS1.2 million project is two months completed. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown risks. Most of the project's reserves have not been spent. The risk manager, who is also the project schedule manager, establishes monthly risk management reviews to evaluate performance. So far, the project has missed 50% of the planned risk mitigation milestones. Based on this project data, what technique should the risk manager recommend to improve the risk management process?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Increase the risk manager's position to a full-time position and acquire a dedicated project schedule lead.
- B. Adjust project risk thresholds to increase the number of residual risks on the project.
- C. Increase the frequency of risk status meetings and update the risk management plan. — đáp án hiện tại
- D. Perform a variance analysis and potentially allocate more reserves to improve risk mitigation.