Câu 79: PMI Risk Management Professional
A project manager is developing the risk management process and schedules a risk planning workshop at the start of the project. Upon receiving the invitation, a senior stakeholder emails the project manager stating that a risk management plan is not needed since this is a small project, and lack of a plan will reduce…
Nội dung câu hỏi
A project manager is developing the risk management process and schedules a risk planning workshop at the start of the project. Upon receiving the invitation, a senior stakeholder emails the project manager stating that a risk management plan is not needed since this is a small project, and lack of a plan will reduce costs. Which of the following should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Advise the stakeholder that risk management is a valuable undertaking and must be applied to all projects to some degree. — đáp án hiện tại
- B. Cancel the workshop, as the stakeholder is senior and risk management is an optional process, especially on smaller projects.
- C. Continue with the workshop, but remove the stakeholder from the list of attendees.
- D. Review the scope in an attempt to save money in other areas of the project to provide funding for the risk management activities.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.