Câu 51: PMI Risk Management Professional
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progr…
Nội dung câu hỏi
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress. How should the project manager handle stakeholder expectations?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Discuss the risk response strategies with the stakeholders.
- B. Ensure the risk register includes all identified risks.
- C. Develop a communication plan to share updates on risks. — đáp án hiện tại
- D. Add buffers to the schedule to accommodate risk.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.