Câu 81: PMI-SP: PMI Scheduling Professional Practice Test

John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure: Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?

Nội dung câu hỏi

John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure: Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?

Minh họa câu hỏi

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Zero — đáp án hiện tại
  2. B. One
  3. C. Four
  4. D. Five