Câu 81: PMI-SP: PMI Scheduling Professional Practice Test
John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure: Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?
Nội dung câu hỏi
John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure: Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Zero — đáp án hiện tại
- B. One
- C. Four
- D. Five
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.