Câu 60: PMI-SP: PMI Scheduling Professional Practice Test
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25…
Nội dung câu hỏi
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Perform resource leveling for the project.
- B. Crash the project schedule.
- C. Fast track the project. — đáp án hiện tại
- D. Remove things from the project scope.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.