Câu 76: PMI-SP: PMI Scheduling Professional Practice Test
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this project's to-complete performance inde…
Nội dung câu hỏi
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this project's to-complete performance index based on the current BAC?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 1.02 — đáp án hiện tại
- B. 0.010
- C. 0.75
- D. 0.95
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.