You are the project manager for your company. You are working with the activities defined in the figure below. What will happen to your project if Activity F takes five additional days to complete than what was expected?

Nội dung câu hỏi

You are the project manager for your company. You are working with the activities defined in the figure below. What will happen to your project if Activity F takes five additional days to complete than what was expected?

Minh họa câu hỏi

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Your project's critical path will shift to ACFI.
  2. B. Your project will be late by five days. — đáp án hiện tại
  3. C. Your project can still complete on time as float is available on Activity I.
  4. D. Your project will now have two critical paths.