Câu 79: PMI-SP: PMI Scheduling Professional Practice Test

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure: You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help of…

Nội dung câu hỏi

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure: You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk event?

Minh họa câu hỏi

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Five days
  2. B. Four days
  3. C. Eleven days
  4. D. Zero — đáp án hiện tại