Câu 79: PMI-SP: PMI Scheduling Professional Practice Test
You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure: You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help of…
Nội dung câu hỏi
You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure: You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk event?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Five days
- B. Four days
- C. Eleven days
- D. Zero — đáp án hiện tại