Câu 38: PMI-SP: PMI Scheduling Professional Practice Test

You are the project manager for the GRT Project in your organization. You have created your time duration estimates based on historical information, but the estimates are not holding true in your current project. Unfortunately, many activities are late. You have decided to create a PERT estimate with your project team…

Nội dung câu hỏi

You are the project manager for the GRT Project in your organization. You have created your time duration estimates based on historical information, but the estimates are not holding true in your current project. Unfortunately, many activities are late. You have decided to create a PERT estimate with your project team for each of their activities. What is the formula used for PERT?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. O+M+P
  2. B. (O+M+P)/3
  3. C. (O+4M+P)/6 — đáp án hiện tại
  4. D. Average of the estimates