Câu 27: PMI-SP: PMI Scheduling Professional Practice Test
Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information,…
Nội dung câu hỏi
Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. -$98,217.78
- B. -$44,198
- C. $441,025.64 — đáp án hiện tại
- D. $243,219.78
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.