Câu 32: PMI-SP: PMI Scheduling Professional Practice Test

You work as a project manager for BlueWell Inc. Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?

Nội dung câu hỏi

You work as a project manager for BlueWell Inc. Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Project Schedule Management Plan
  2. B. Project Staffing Management Plan — đáp án hiện tại
  3. C. Project Human Resources Management Plan
  4. D. Project Communications Management Plan