Câu 92: PMI-SP: PMI Scheduling Professional Practice Test

Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and he…

Nội dung câu hỏi

Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and her project management software to perform schedule network analysis. What other tool Winnie can use to help and generate an updated project schedule?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Critical path method
  2. B. Schedule management plan
  3. C. Scheduling tool — đáp án hiện tại
  4. D. Critical chain method