Câu 98: PMI-SP: PMI Scheduling Professional Practice Test

Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?

Nội dung câu hỏi

Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Cost variances and Cost Performance Index
  2. B. Scope baseline
  3. C. Performance measurement baseline — đáp án hiện tại
  4. D. Schedule variances, planned value, and the Schedule Performance Index