Câu 5: PMI-SP: PMI Scheduling Professional Practice Test
Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.
Nội dung câu hỏi
Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Quality inspections and compliance
- B. Location, logistics, and resource availability analysis — đáp án hiện tại
- C. Labor productivity studies from previous similar projects in the area — đáp án hiện tại
- D. The average price of general labor in the area — đáp án hiện tại