Câu 8: PMI-SP: PMI Scheduling Professional Practice Test

John works as a project manager for BlueWell Inc. His project has a budget of $795,000 and he has spent $325,000 on the project. But, he has completed only 40 percent of the project work till now. Management wants to know what the project's cost performance index is. What value will John report?

Nội dung câu hỏi

John works as a project manager for BlueWell Inc. His project has a budget of $795,000 and he has spent $325,000 on the project. But, he has completed only 40 percent of the project work till now. Management wants to know what the project's cost performance index is. What value will John report?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. 0.76
  2. B. 0.85
  3. C. 0.80
  4. D. 0.92 — đáp án hiện tại