Câu 62: PMI-SP: PMI Scheduling Professional Practice Test

You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?

Nội dung câu hỏi

You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. A significant point in the project — đáp án hiện tại
  2. B. A goal of reaching a significant delivery of project benefits by an identified date
  3. C. An imposed date for the project to reach a given point
  4. D. The completion of a project activity that is crucial to project completion