Câu 73: PMI-SP: PMI Scheduling Professional Practice Test
You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure: Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration…
Nội dung câu hỏi
You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure: Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 32 days
- B. 29 days
- C. 27 days
- D. 26 days — đáp án hiện tại