Câu 400: Project Management Professional (PMBOK 6 and 7)

A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of the team. What should the project manager do?

Nội dung câu hỏi

A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of the team. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask the team member to bring up the concern in the next daily meeting — đáp án hiện tại
  2. B. Send an email explaining the issue to all team members
  3. C. Reassign the task to another team member
  4. D. Move the task to the next sprint