Câu 100: Project Management Professional (PMBOK 6 and 7)
A project manager is managing a project that has a new sponsor who is cutting the budget. As a servant leader, how should the project manager handle the budget cuts with the team?
Nội dung câu hỏi
A project manager is managing a project that has a new sponsor who is cutting the budget. As a servant leader, how should the project manager handle the budget cuts with the team?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Notify the project sponsor that the budget reduction will require a schedule slip and scope reduction.
- B. Collaborate with the team to assess the impact of the change on the project and recommend an updated project plan. — đáp án hiện tại
- C. Inform each team member that they must release a portion of their budget but must remain on schedule with no change to the scope.
- D. Meet with the schedule coordinator and financial analyst to tell them which budget lines to reduce and where to release slack.