A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization. The project team is experiencing low morale and poor teamwork. What should the project manager do to improve morale?
Nội dung câu hỏi
A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization. The project team is experiencing low morale and poor teamwork. What should the project manager do to improve morale?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Identify the wants and aspirations of the team
- B. Build team connections and emotional bonds — đáp án hiện tại
- C. Forge consensus through team participation
- D. Set goals and push the team to achieve the goals