Câu 147: Project Management Professional (PMBOK 6 and 7)

A new law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout. What should the project manager do?

Nội dung câu hỏi

A new law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Meet the sponsor to ask for additional time and budget increase
  2. B. Minimize the scope to catch the cost and schedule baseline
  3. C. Update the project plan because the law is an obligation for the project
  4. D. Assess and prioritize the impact of the new law on the project plan — đáp án hiện tại