Câu 385: Project Management Professional (PMBOK 6 and 7)

An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price…

Nội dung câu hỏi

An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price. What should the product owner do about this situation?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Reprioritize the backlog based on value and cost of delay divided by duration. — đáp án hiện tại
  2. B. Switch to a predictive approach to prevent any further delays to completion.
  3. C. Reprioritize the backlog based on story size and competence availability.
  4. D. Remove low-value items from the backlog to compensate for the higher cost.