Câu 40: Project Management Professional (PMBOK 6 and 7)
As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail. What should the project manager do first to decide how to manage this project?
Nội dung câu hỏi
As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail. What should the project manager do first to decide how to manage this project?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Select a predictive development life cycle based on the team's experience
- B. Determine the most appropriate life cycle approach for the project — đáp án hiện tại
- C. Register all requirements into a backlog for further detailed analysis
- D. Split the requirements, put them into two separate projects, and apply different approaches
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.