Câu 263: Project Management Professional (PMBOK 6 and 7)

A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been…

Nội dung câu hỏi

A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed. What should the project manager do immediately about this situation?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Register the schedule risk and present the new resources requirement to the change management board for schedule recovery.
  2. B. Prepare a monthly report by highlighting the completed deliverables and communicate the delay to management.
  3. C. Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay. — đáp án hiện tại
  4. D. Ask the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team.