CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 320: Project Management Professional (PMBOK 6 and 7)

A project manager notices that a new junior team member's suggestions are constantly rejected by senior team members. The senior team members find the suggestions valid and innovative, but unrealistic. Following several project assignments, the senior members request to have the junior team member removed. What should…

Nội dung câu hỏi

A project manager notices that a new junior team member's suggestions are constantly rejected by senior team members. The senior team members find the suggestions valid and innovative, but unrealistic. Following several project assignments, the senior members request to have the junior team member removed. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Remove possible conflicts from future project assignments.
  2. B. Accept the demands and remove the junior team member.
  3. C. Group the new team members together for training purposes.
  4. D. Encourage further and deeper discussions among team members. — đáp án hiện tại

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề