Câu 282: Project Management Professional (PMBOK 6 and 7)
During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics:1,600 rpm (rate-per-minute) -> stops…
Nội dung câu hỏi
During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics:1,600 rpm (rate-per-minute) -> stops working and crashes the system1,500 rpm (rate-per-minute) -> warns of max rate allowed1,400 rpm (rate-per-minute) -> reduces the power and brakes the engineWhich of the following statements is correct?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 1,600 rpm is a project risk, 1,500 rpm is an event that triggers a response strategy, and 1,400 rpm is a project issue.
- B. 1,600 rpm is a project issue, 1,500 rpm is an event that triggers a response strategy, and 1,400 rpm is a project risk.
- C. 1,600 rpm is a project issue, 1,500 rpm is a project risk, and 1,400 rpm is an event that triggers a response strategy. — đáp án hiện tại
- D. 1,600 rpm is an event that triggers a response strategy, 1,500 rpm is a project issue, and 1,400 rpm is a project risk.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.