Câu 242: Project Management Professional (PMBOK 6 and 7)

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

Nội dung câu hỏi

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Explain to the stakeholder that these are the approved templates for the reports.
  2. B. Ask the project team to review and modify all of these reports.
  3. C. Ensure that the reports comply with the communications management plan. — đáp án hiện tại
  4. D. Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.