Câu 190: Project Management Professional (PMBOK 6 and 7)

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Nội dung câu hỏi

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Minh họa câu hỏi

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask the product owner if some low-priority stories could be cut from the sprint
  2. B. Continue with the sprint as the progress shows buffers for potential interruptions
  3. C. Ask the project team to select any additional stories as they have additional capacity than planned
  4. D. Continue with the sprint work as planned and keep monitoring — đáp án hiện tại