Câu 207: Project Management Professional (PMBOK 6 and 7)

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting. The ongoing conflict is preventing tasks and deliverables from being completed. The project manager contemplates changing their leadership style. What should the project manager do?

Nội dung câu hỏi

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting. The ongoing conflict is preventing tasks and deliverables from being completed. The project manager contemplates changing their leadership style. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Review the set of responsibilities with the team member — đáp án hiện tại
  2. B. Avoid the team member to prevent further conflicts
  3. C. Escalate the situation to the project sponsor
  4. D. Review the personnel skill documents