Câu 341: Project Management Professional (PMBOK 6 and 7)
During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the quality standards required by regulations. What should the project manager have done to avoid this?
Nội dung câu hỏi
During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the quality standards required by regulations. What should the project manager have done to avoid this?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Ensured that the project sponsor understood the scope of the project to avoid any future complaints
- B. Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks
- C. Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration — đáp án hiện tại
- D. Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.