CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 276: Project Management Professional (PMBOK 6 and 7)

A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished. How should the project manager approach this situati…

Nội dung câu hỏi

A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished. How should the project manager approach this situation?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Request that the customer reviews and clarifies feature definitions for the current sprint — đáp án hiện tại
  2. B. Send a burndown chart of the current sprint to the customer and seek clarifications.
  3. C. Educate the customer and have them participate in daily standup meetings.
  4. D. Schedule weekly meetings and product reviews with the customer to clarify requirements

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề