A new regulation has been approved that will impact the deliverables in the fourth phase of the project. The delivery is following an iterative approach and is currently completing the second phase. What should the project manager do next?

Nội dung câu hỏi

A new regulation has been approved that will impact the deliverables in the fourth phase of the project. The delivery is following an iterative approach and is currently completing the second phase. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Consult with the project sponsor to discuss a cost increase
  2. B. Acquire approval for an exception to the implementation of the new regulation
  3. C. Get approval for the additional budget from the steering committee
  4. D. Meet with subject matter experts (SMEs) to access the impact to objectives — đáp án hiện tại