Câu 288: Project Management Professional (PMBOK 6 and 7)

A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months. What should the pr…

Nội dung câu hỏi

A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months. What should the project manager do first?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Set up a steering committee session to review the project delay.
  2. B. Continue with the approved design so that the project is not delayed.
  3. C. Log the technical design delay as a risk in the project risk log. — đáp án hiện tại
  4. D. Ask the steering committee to approve a new technical design.