Câu 288: Project Management Professional (PMBOK 6 and 7)
A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months. What should the pr…
Nội dung câu hỏi
A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months. What should the project manager do first?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Set up a steering committee session to review the project delay.
- B. Continue with the approved design so that the project is not delayed.
- C. Log the technical design delay as a risk in the project risk log. — đáp án hiện tại
- D. Ask the steering committee to approve a new technical design.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.