An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and follow-up calls with key stakeholders. The team seems to be disengaged. How should the project manager approach this situation?
Nội dung câu hỏi
An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and follow-up calls with key stakeholders. The team seems to be disengaged. How should the project manager approach this situation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Reduce the number of internal and external meetings.
- B. Schedule one-to-one meetings and team-building meetings. — đáp án hiện tại
- C. Review team assignments and reduce the workload.
- D. Give the team members a few days off to reduce stress_