Câu 391: Project Management Professional (PMBOK 6 and 7)

After signing an agreement with a vendor, the project manager notices that the vendor is continuously asking for changes on the procurement statement of work(SOW). These changes would improve the project outcome. What should the project manager do next?

Nội dung câu hỏi

After signing an agreement with a vendor, the project manager notices that the vendor is continuously asking for changes on the procurement statement of work(SOW). These changes would improve the project outcome. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Consult the list of selected vendors for the bid and evaluate a possible change of vendor.
  2. B. Revise the procurement control process to avoid undesired changes that might affect the schedule.
  3. C. Assess the situation as an opportunity for improvement and perform a risk analysis. — đáp án hiện tại
  4. D. Conduct an audit on the procurement process and inform the vendor about the audit's observations.