Câu 66: Project Management Professional (PMBOK 6 and 7)
A project manager has received an updated earned value analysis report. The following are the key findings from the report:* Budget at completion = US$1 million* Earned value = US$0,7 million* Actual cost = US$0,75 million* Cost performance index = 0,933Based on this information, what should the project manager conclu…
Nội dung câu hỏi
A project manager has received an updated earned value analysis report. The following are the key findings from the report:* Budget at completion = US$1 million* Earned value = US$0,7 million* Actual cost = US$0,75 million* Cost performance index = 0,933Based on this information, what should the project manager conclude about project performance?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The project will be completed exactly as planned
- B. The project will be easier to complete than planned
- C. The project will be difficult to complete as planned — đáp án hiện tại
- D. The project will not be completed as planned