Câu 333: Project Management Professional (PMBOK 6 and 7)
A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management. What should the project manager do first?
Nội dung câu hỏi
A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management. What should the project manager do first?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Assess the time overrun, and start implementation to avoid additional delays
- B. Motivate the team to avoid the frustration of working on a prolonged project
- C. Request a provisional budget increase to avoid any budget overruns
- D. Review the benefits of the proposed changes in relation to the business case — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.