Câu 118: Project Management Professional (PMBOK 6 and 7)

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The licensing cost is significant. What should the project manager do next?

Nội dung câu hỏi

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The licensing cost is significant. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Evaluate the impact of nonrenewal of the license. — đáp án hiện tại
  2. B. Escalate the licensing issue to the product owner.
  3. C. Add a spike to the backlog for an alternative design.
  4. D. Raise a change request to secure the renewal.