CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 45: Project Management Professional (PMBOK 6 and 7)

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency an…

Nội dung câu hỏi

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Consult the risk register for an appropriate planned risk response and implement. — đáp án hiện tại
  2. B. Revise the project management plan and move the task to a time when the technical resource will be available.
  3. C. Review the business requirement with stakeholders and exclude the task assigned to the technical resource.
  4. D. Update the lessons learned report and the risk log to reflect that this risk has materialized.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề