Câu 4: Project Management Professional (PMBOK 6 and 7)
A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is on hold until the assigned…
Nội dung câu hỏi
A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Meet with the design team manager to inform them of the current status and request an additional designer
- B. Ask the software engineer to move forward without completing the important feature
- C. Contact the design team manager and ask to reconsider the priority list based on the latest situation
- D. Meet with the designer to share the current status and develop a solution to complete the task — đáp án hiện tại