Câu 335: Project Management Professional (PMBOK 6 and 7)

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements. What should the project manager do?

Nội dung câu hỏi

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Request additional budget because additional features are being added
  2. B. Ask the product owner to add the additional features to the requirements
  3. C. Encourage the team to continue, as this will eventually help the customer
  4. D. Ask the team to focus on and deliver only the agreed-upon features — đáp án hiện tại