Câu 373: Project Management Professional (PMBOK 6 and 7)

During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not I convinced that the return on investment (ROI) can be achieved. How should the project manager address this issue?

Nội dung câu hỏi

During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not I convinced that the return on investment (ROI) can be achieved. How should the project manager address this issue?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Analyze the bounds of negotiations for project agreements.
  2. B. Re-visit the project charter and seek other alternatives. — đáp án hiện tại
  3. C. Speak with the CEO and ask for their support to approve the offer.
  4. D. Proceed and issue the purchase order as this project is important.