Câu 373: Project Management Professional (PMBOK 6 and 7)
During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not I convinced that the return on investment (ROI) can be achieved. How should the project manager address this issue?
Nội dung câu hỏi
During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not I convinced that the return on investment (ROI) can be achieved. How should the project manager address this issue?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Analyze the bounds of negotiations for project agreements.
- B. Re-visit the project charter and seek other alternatives. — đáp án hiện tại
- C. Speak with the CEO and ask for their support to approve the offer.
- D. Proceed and issue the purchase order as this project is important.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.