Câu 33: Project Management Professional (PMBOK 6 and 7)
A team is working on implementing a communications system when the client says that they are considering closing the project. The project manager schedules an urgent meeting with the client to understand why the project is at risk. Which two tools or techniques can the project manager use to influence the client's dec…
Nội dung câu hỏi
A team is working on implementing a communications system when the client says that they are considering closing the project. The project manager schedules an urgent meeting with the client to understand why the project is at risk. Which two tools or techniques can the project manager use to influence the client's decision to keep the project active? (Choose two.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Alternatives analysis — đáp án hiện tại
- B. Voting
- C. Cost-benefit analysis — đáp án hiện tại
- D. Multi-criteria decision making
- E. Autocratic decision making
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.