Câu 35: Project Management Professional (PMBOK 6 and 7)

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals. What two options will help the team initially address this obstacle? (Choose two.)

Nội dung câu hỏi

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals. What two options will help the team initially address this obstacle? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Escalate the issue to the project sponsor
  2. B. Review and update dependencies — đáp án hiện tại
  3. C. Schedule a retrospective
  4. D. Conduct a root cause analysis — đáp án hiện tại
  5. E. Create a risk management plan